home
Donate now

Menu

The Swiss Open-Air Museum is – finally – getting a schoolhouseConstruction diary schoolhouse Unterheid

The schoolhouse in Unterheid, near Meiringen (BE), is currently being dismantled stone by stone so that it can be rebuilt at the Swiss Open-Air Museum. We’re keeping a construction diary, packed with all the latest about the relocation work, construction progress, the history of the building, background information and other interesting facts about this special project.    

Share page:
Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.

Construction diary entry no. 9, August 2025Floor by floor - the construction is progressing

Visitors to Ballenberg this season will be able to see the almost finished shell of the schoolhouse relocated from Unterheid, near Meiringen (Bern), at the construction site. Reconstruction is progressing rapidly, although bricklaying with pure lime mortar takes time, as only a few layers of stone can be freshly laid on top of one another at a time. However, it is important that we adhere to schedule given that from as early as October, the temperatures could drop so low that the bricklayers would no longer be able to continue working. At the moment, however, the biggest challenge faced is the ongoing heatwave. If the mortar dries out too quickly, cracks can form and the mortar crumbles. This is why the bricklayers cover the fresh mortar with wet cloths at the end of the day – this delays drying and curing.

Image caption: At present, skips containing the stone material for the partition walls are still located in the classroom. The historic panels of the classroom will only be restored when finishing the interior.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

The first floor flooring that lies on top of these beams has also been laid. This was replaced with new materials because the planks of the old floor planks could no longer support the required load. The planks have been made to their original dimensions. The carpenters erected the original timber structure on top of the brick interior wall on the ground floor, which serves as the partition wall between the classroom and the hallway on the first floor. The masons are also in the process of constructing the parapets on the exterior walls, which will later support the window frames. The classroom’s window openings will soon be visible.

Pay us a visit and experience the shell of the building up close – the season runs until 2 November.

Image caption: The window frames on the 2nd floor will now be walled up.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Construction diary schoolhouse Unterheid

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The 1st and 2nd floors are separated by a plank ceiling and a boarded floor. The planks have been inserted into the existing grooves in the beams.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Although the partition walls are not yet finished, the layout of the former teachers’ quarters on the 2nd floor can be clearly observed thanks to the timber construction

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The timber structure of the interior wall has already been erected. The surrounding walls are now being built.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A look inside the ground floor room that was previously used as a stable. The ceiling beams and ground floor ceiling, or rather the floor on the first floor, have already been installed.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Each stone is carefully positioned and the gaps filled with mortar and spandrel stones.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The brickwork in the former cellar is finished. As it will house a plant room and toilet in the open-air museum, the floor was made from a concrete slab.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Thanks to the detailed plans prepared in advance, the particularly prominent bricks can be returned to their original position. 

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The bricks, which were marked during the dismantling process to indicate which storey they were from and which direction they were facing, are sorted.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Right next to the construction site, there is a specially equipped mixing site where lime mortar is produced.

  • Der letzte Stein ist abgebaut, das Schulhaus Unterheid ist auf dem Weg auf den Ballenberg.

    Reconstruction is underway – the schoolhouse is being rebuilt brick by brick.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Masons and carpenters work hand in hand during the reconstruction process. The first door frames are already in place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The hollow spaces between the quarry stones are filled with slate, which is pressed into the mortar.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The carpenters also follow plans to ensure that every timber component is in its proper place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Beams are inspected for damage and some parts are replaced or reconstructed.

  • Für Mörtel, Verputz und Kalkanstrich wurden Kalksteine in einem Ofen auf über 1000°C erhitzt und dann nach dem Abkühlen mit Wasser «gelöscht».
  • Lagerung der Holzelemente vom Schulhaus Unterheid.

    The wooden elements are being stored, and damaged or missing wooden parts are being reconstructed.

  • Das Schulhaus Unterheid ist vollständig abgebaut.

    The building has been completely dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The last walls are being dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Prominent bricks are measured and recorded on the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The bricks are numbered according to the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A piece of wood with a drawing was discovered while dismantling.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Leta Büchi, a qualified excavator, and Patrick Bürgin, project manager for the translocation of the schoolhouse, inspect the structural changes to the jetty.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Negative recesses in the windows indicate that they were replaced over the course of time.

  • Das neue Zuhause, das Fundament vom Schulhaus aus Unterheid steht.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.

The relocation is supported by the Ghelma AG Baubetriebe in Meiringen. Thank you very much!

The relocation is supported by the Burgergemeinde Bern. Thank you very much!

Ballenberg
Swiss Open-Air Museum

Museumsstrasse 100
CH-3858 Hofstetten bei Brienz

+41 33 952 10 30
info@ballenberg.ch

Opening hours

10 April to 2 November 2025
10 am to 5 pm daily

Follow us