home
Donate now

Menu

The Swiss Open-Air Museum is – finally – getting a schoolhouse – Construction diary schoolhouse Unterheid

The schoolhouse in Unterheid, near Meiringen (BE), is currently being dismantled stone by stone so that it can be rebuilt at the Swiss Open-Air Museum. We’re keeping a construction diary, packed with all the latest about the relocation work, construction progress, the history of the building, background information and other interesting facts about this special project.    

Share page:
Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.

Construction diary entry no. 13, November 2026 – The exterior construction is as good as finished!

Back in July, the rear of the building was finished with coarse plaster and whitewash, just as it was at the former location. After this, we took a summer break of several weeks, as the high temperatures and low humidity were not ideal for working with lime plaster. Conditions finally improved in September, so the final work on the façades of the schoolhouse took place in late summer and early autumn.

The other exterior walls have received a much more comprehensive treatment than the rear of the building. Because they were visible from the road passing by at the former location, they were plastered with greater care and effort at the time of construction in 1830. At that time, the wall surfaces were given painted façade decorations in addition to a fine plaster and several layers of whitewash. They consisted of a painted pyramid-shaped diamond effect on the corners of the building, and on the main façade there was an inscription with the year of construction and star-shaped decorations in the gables and a plinth made to look like large stone blocks.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Only fragments of the painted decorations were preserved at the former location and these were pieced back together during the reconstruction of the schoolhouse. Despite this, the fragments found at the old location were sufficient to determine the colours and dimensions and to make out the text. As with the mortar and plaster, the paint for the wall decorations was produced using historical recipes. A lime-casein paint was used that could already be found on the historic schoolhouse. This paint is a mixture of slaked lime, casein (milk protein, usually from low-fat quark) and natural pigments.

Not only have the walls of the schoolhouse been completed, the final layer has also been installed on the roof in the form of new slate shingles. The schoolhouse didn’t have a slate roof in its most recent form, but archive records show that this was the original roof covering – a peculiarity in the Bernese Oberland, where roofs traditionally had wooden shingles.

The carpenters have also been busy on the construction site: the schoolhouse has got its porch back. Because various boards of the partly elaborately decorated cladding were already rotten, many of them had to be replaced with new wood. It won’t be long before the new material darkens due to the weather. Then it will no longer be so easy to distinguish it from the historical cladding.

Once the exterior construction is almost complete, the next step is the interior of the schoolhouse, as there is still a lot to do there.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Just in time for the second construction phase, the schoolhouse is being featured on Schweiz aktuell. Watch the programme to learn more about the development and current status of the project and get insights into the construction site and future plans.

Construction diary schoolhouse Unterheid

  • Die Fassade des Schulhauses aus Unterheid ist so gut wie fertig

    After two and a half years, the scaffolding has been dismantled and the magnificent façade painting is visible.

  • Das Schieferdach des Schulhauses aus Unterheid ist so gut wie fertig

    The roof was covered with slate shingles again, just like it was in 1830.

  • Die Diamantquaderung an den Gebäudeecken erzeugt einen dreidimensionalen Eindruck. Die Fugenstriche im Sockelbereich fehlen noch.

    The diamond effect on the corners of the building gives the impression of being three-dimensional. The scored joints in the plinth still need to be done.

  • Die Rekonstruktion der filigranen Giebelmalerei erfordert eine ruhige Hand

    Piecing the intricate gable painting back together requires a steady hand.

  • Kontrast zwischen grobem Putz auf der Gebäuderückseite und feinem Putz an den übrigen drei Wandflächen

    The contrast between the coarse plaster on the rear of the building and the fine plaster on the other three walls.

  • Nach dem Einritzen der Hilfslinien erhält der Feinputz in noch feuchtem Zustand zwei Kalkanstriche im sogenannten Fresco-Verfahren

    After scoring the guidelines and while the plaster is still damp, the fine plaster receives two coats of whitewash using what is known as the fresco process.

  • Die Hilfslinien für die spätere aufgemalte Diamantquaderung werden in den noch feuchten Feinputz geritzt

    The guidelines for the painted diamond effect are scored into the fine plaster while it is still damp.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.
  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The historic tiled stove was rebuilt in the classroom of the museum building.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The shell is now almost complete.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The original roof structure was rotten in many places, which explains why a lot of new timber has been used during the reconstruction.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A view of the gallery on the second floor.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    As at the former location, various objects have been embedded in the gables during the reconstruction.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The roof has a shingle covering and is now watertight. The final layer of slate shingles is still missing.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The exterior walls are finished. During the winter, the filled bays of the interior walls will be lined with brickwork.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The 1st and 2nd floors are separated by a plank ceiling and a boarded floor. The planks have been inserted into the existing grooves in the beams.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Although the partition walls are not yet finished, the layout of the former teachers’ quarters on the 2nd floor can be clearly observed thanks to the timber construction

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The timber structure of the interior wall has already been erected. The surrounding walls are now being built.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A look inside the ground floor room that was previously used as a stable. The ceiling beams and ground floor ceiling, or rather the floor on the first floor, have already been installed.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Each stone is carefully positioned and the gaps filled with mortar and spandrel stones.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The brickwork in the former cellar is finished. As it will house a plant room and toilet in the open-air museum, the floor was made from a concrete slab.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Thanks to the detailed plans prepared in advance, the particularly prominent bricks can be returned to their original position. 

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The bricks, which were marked during the dismantling process to indicate which storey they were from and which direction they were facing, are sorted.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Right next to the construction site, there is a specially equipped mixing site where lime mortar is produced.

  • Der letzte Stein ist abgebaut, das Schulhaus Unterheid ist auf dem Weg auf den Ballenberg.

    Reconstruction is underway – the schoolhouse is being rebuilt brick by brick.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Masons and carpenters work hand in hand during the reconstruction process. The first door frames are already in place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The hollow spaces between the quarry stones are filled with slate, which is pressed into the mortar.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The carpenters also follow plans to ensure that every timber component is in its proper place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Beams are inspected for damage and some parts are replaced or reconstructed.

  • Für Mörtel, Verputz und Kalkanstrich wurden Kalksteine in einem Ofen auf über 1000°C erhitzt und dann nach dem Abkühlen mit Wasser «gelöscht».
  • Lagerung der Holzelemente vom Schulhaus Unterheid.

    The wooden elements are being stored, and damaged or missing wooden parts are being reconstructed.

  • Das Schulhaus Unterheid ist vollständig abgebaut.

    The building has been completely dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The last walls are being dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Prominent bricks are measured and recorded on the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The bricks are numbered according to the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A piece of wood with a drawing was discovered while dismantling.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Leta Büchi, a qualified excavator, and Patrick Bürgin, project manager for the translocation of the schoolhouse, inspect the structural changes to the jetty.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Negative recesses in the windows indicate that they were replaced over the course of time.

  • Das neue Zuhause, das Fundament vom Schulhaus aus Unterheid steht.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.

The relocation is supported by the Ghelma AG Baubetriebe in Meiringen. Thank you very much!

The relocation is supported by the Burgergemeinde Bern. Thank you very much!

The relocation is supported by the Katharina Wiedmer Foundation. Thank you very much!

Ballenberg
Swiss Open-Air Museum

Museumsstrasse 100
CH-3858 Hofstetten bei Brienz

+41 33 952 10 30
info@ballenberg.ch

Opening hours
15 April to 7 November 2027
10 am to 5 pm daily

Opening hours Administration
2 November 2026 to 14 April 2027
Mon - Fri: 8.30 to 11.30 am, 1.30 to 4.30 pm

Follow us