home
Donate now

Menu

The Swiss Open-Air Museum is – finally – getting a schoolhouseConstruction diary schoolhouse Unterheid

The schoolhouse in Unterheid, near Meiringen (BE), is currently being dismantled stone by stone so that it can be rebuilt at the Swiss Open-Air Museum. We’re keeping a construction diary, packed with all the latest about the relocation work, construction progress, the history of the building, background information and other interesting facts about this special project.    

Share page:
Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.

Construction diary entry no. 12, July 2026The second phase of construction is in full swing

After the completion of the shell at the end of last year, the second phase of construction has now begun. This includes plastering the wall surfaces, reconstructing the façade paintings, windows and porch, installing the panels and covering the roof with slate shingles.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Thanks to the warmer temperatures, we have been able to start plastering the masonry. The interior walls already had holes filled and received a partial base coat of plaster in the warm weeks of spring. Now it’s the turn of the façades. Working at full speed with a team of seven, the restorer is plugging the cavities between the bricks and will then apply a primer. This forms a stable substrate for the subsequent base coat. Like the mortar in the masonry, the plasters are lime-based, without added cement. The protracted heatwave in June has made working a challenge, not only because of the need to work at high temperatures but also because of the risk of the plaster “burning”. This means that the plaster sets or dries too quickly and therefore cracks and crumbles. To prevent this, the plastered surfaces must be regularly kept moist and the intense sunlight reduced by means of jute sheets suspended on the scaffolding.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Just in time for the second construction phase, the schoolhouse is being featured on Schweiz aktuell. Watch the programme to learn more about the development and current status of the project and get insights into the construction site and future plans.

Construction diary schoolhouse Unterheid

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.
  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The historic tiled stove was rebuilt in the classroom of the museum building.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The shell is now almost complete.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The original roof structure was rotten in many places, which explains why a lot of new timber has been used during the reconstruction.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A view of the gallery on the second floor.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    As at the former location, various objects have been embedded in the gables during the reconstruction.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The roof has a shingle covering and is now watertight. The final layer of slate shingles is still missing.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The exterior walls are finished. During the winter, the filled bays of the interior walls will be lined with brickwork.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The 1st and 2nd floors are separated by a plank ceiling and a boarded floor. The planks have been inserted into the existing grooves in the beams.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Although the partition walls are not yet finished, the layout of the former teachers’ quarters on the 2nd floor can be clearly observed thanks to the timber construction

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The timber structure of the interior wall has already been erected. The surrounding walls are now being built.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A look inside the ground floor room that was previously used as a stable. The ceiling beams and ground floor ceiling, or rather the floor on the first floor, have already been installed.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Each stone is carefully positioned and the gaps filled with mortar and spandrel stones.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The brickwork in the former cellar is finished. As it will house a plant room and toilet in the open-air museum, the floor was made from a concrete slab.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Thanks to the detailed plans prepared in advance, the particularly prominent bricks can be returned to their original position. 

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The bricks, which were marked during the dismantling process to indicate which storey they were from and which direction they were facing, are sorted.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Right next to the construction site, there is a specially equipped mixing site where lime mortar is produced.

  • Der letzte Stein ist abgebaut, das Schulhaus Unterheid ist auf dem Weg auf den Ballenberg.

    Reconstruction is underway – the schoolhouse is being rebuilt brick by brick.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Masons and carpenters work hand in hand during the reconstruction process. The first door frames are already in place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The hollow spaces between the quarry stones are filled with slate, which is pressed into the mortar.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The carpenters also follow plans to ensure that every timber component is in its proper place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Beams are inspected for damage and some parts are replaced or reconstructed.

  • Für Mörtel, Verputz und Kalkanstrich wurden Kalksteine in einem Ofen auf über 1000°C erhitzt und dann nach dem Abkühlen mit Wasser «gelöscht».
  • Lagerung der Holzelemente vom Schulhaus Unterheid.

    The wooden elements are being stored, and damaged or missing wooden parts are being reconstructed.

  • Das Schulhaus Unterheid ist vollständig abgebaut.

    The building has been completely dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The last walls are being dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Prominent bricks are measured and recorded on the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The bricks are numbered according to the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A piece of wood with a drawing was discovered while dismantling.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Leta Büchi, a qualified excavator, and Patrick Bürgin, project manager for the translocation of the schoolhouse, inspect the structural changes to the jetty.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Negative recesses in the windows indicate that they were replaced over the course of time.

  • Das neue Zuhause, das Fundament vom Schulhaus aus Unterheid steht.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.

The relocation is supported by the Ghelma AG Baubetriebe in Meiringen. Thank you very much!

The relocation is supported by the Burgergemeinde Bern. Thank you very much!

Ballenberg
Swiss Open-Air Museum

Museumsstrasse 100
CH-3858 Hofstetten bei Brienz

+41 33 952 10 30
info@ballenberg.ch

Opening hours
9 April to 1 November 2026
10 am to 5 pm daily

Opening hours Administration
8 am to 6 pm daily

Follow us